+0  
 
0
383
1
avatar

Five people can develop one software application in 13 days. If 2 people are suspended after the 4th day, how many total days will it take to complete the software application?

 Aug 17, 2020
 #1
avatar+36915 
0

5 people x 13 days = 65 people days to complete

 

5 people x 4 days = 20 people days completed     leaving

          45 people days to completion by 3 people.......    15 days more to complete after suspension

 

    total days   4 + 15 = 19 days total

 Aug 17, 2020

8 Online Users

avatar
avatar
avatar
avatar