A certain work has to be done by 6 workers for 8 days, but 2 of the workers got hurt, thus cannot work. How many days will it take for the rest ofthe workers to do the work? (Please explain how you solved this)
1 job = 6 workers x 8days = 48 worker-days to get the job done
4 workers * 'x' days = 48 worker-days ?
48 worker-days / 4 workers = 12 days to get the job done.
1 job = 6 workers x 8days = 48 worker-days to get the job done
4 workers * 'x' days = 48 worker-days ?
48 worker-days / 4 workers = 12 days to get the job done.