+0  
 
0
637
1
avatar

a builder needs 6.5 cubic meteres of concreate for a job the table below shows the mixture for concreate cement 2 parts sand 4parts smallstones 5 parts water 1 part how many cubic meters of sand does the builder need?

 Feb 12, 2017
 #1
avatar+37084 
0

2 parts + 4 parts + 5 parts + 1 part = 12 parts total of which 4 parts are sand   

4 out of 12   or 4/12 sand  out of 6.5 cubic meters     4/12 x 6.5 =

4/12*6.5 = 2.167 cubic meters of sand

 Feb 12, 2017

1 Online Users

avatar