Five workers have been hired to complete a job. If one additional worker is hired, they could complete the job $8$ days earlier. If the job needs to completed $28$ days earlier, how many additional workers should be hired?
Let the time to complete the job with 5 workers = T days
So......the total man-days for the job is 5T
If one additional worker is hired, the man-days for the job is 6 (T - 8)
So....since the man-days will be the same for the job.....
5T = 6(T - 8)
5T = 6T - 48
48 = T
So the number of man-days to complete the job is 5(48) = 240
So.....to complete the job 28 days earlier
(number of workers needed) * ( 48 - 28) = 240
(number of workers needed) * (20) = 240
number of workers needed = 240 / 20 = 12
So.....(12 - 5) = 7 additional workers should be hired to complete the job 28 days earlier
How many additional workers should be hired?
Hello Lilliam0216!
I assume the 5 workers can complete the job in around 120 hours.
\(\psi =\frac{J}{5\cdot 120h}\\ J=5\cdot 120h\cdot \psi =(5+1)\cdot (120-8)\cdot \psi=(5+x)\cdot (120-28)\cdot \psi\\ 6\cdot 112=(5+x)\cdot 92\\ 672=460+92x\\ x=\frac{672-460}{92}=2.3\color{blue}\to 3\\ 6\cdot t=(5+\color{blue}3)\cdot 92\)
\(t=\frac{8\cdot 92}{6}=\color{blue}122\frac{2}{3}h\)
If the 5 workers completed the work in 122 2/3 hours, 3 additional workers should be hired to save 28 hours.
An additional time specification is absolutely necessary for your question.
!
Let the time to complete the job with 5 workers = T days
So......the total man-days for the job is 5T
If one additional worker is hired, the man-days for the job is 6 (T - 8)
So....since the man-days will be the same for the job.....
5T = 6(T - 8)
5T = 6T - 48
48 = T
So the number of man-days to complete the job is 5(48) = 240
So.....to complete the job 28 days earlier
(number of workers needed) * ( 48 - 28) = 240
(number of workers needed) * (20) = 240
number of workers needed = 240 / 20 = 12
So.....(12 - 5) = 7 additional workers should be hired to complete the job 28 days earlier