+0  
 
+1
758
1
avatar+422 

It takes 36 workers 48 hours to paint a ship. Working at the same rate, how many hours would 24 workers need to paint the ship?

 

Answer Choices

A. 32

B. 56

C. 64

D. 72

 Jan 25, 2019
 #1
avatar+36916 
0

36 w x 48 hr = 1728 worker hours to complete the job

1728 w h /24 w = 72 hrs for only 24 workers 

 Jan 25, 2019

5 Online Users

avatar
avatar
avatar
avatar