It takes 36 workers 48 hours to paint a ship. Working at the same rate, how many hours would 24 workers need to paint the ship?

 

Answer Choices

A. 32

B. 56

C. 64

D. 72

 Jan 25, 2019
 #1
avatar+37146 
0

36 w x 48 hr = 1728 worker hours to complete the job

1728 w h /24 w = 72 hrs for only 24 workers 