It takes four painters working at the same rate $1.25$ work-days to finish a job. If only three painters are available, how many work-days will it take them to finish the job, working at the same rate? Express your answer as a mixed number

 Dec 19, 2021
 #1
avatar
-1

The answer is 2 1/8.

 Dec 19, 2021
 #3
avatar+76 
+2

Would you please explain how you got this answer?

Guinevere  Dec 19, 2021
 #2
avatar+76 
+2

If it takes four painters 1.25 days to finish a job, it would take one person 5 days to finish the same job. If this five days is divided into 3 people, it will take 5/3 days for them to complete the job.

 Dec 19, 2021
 #4
avatar+118608 
0

Nice logic Guinevere  cool

 

You should give yourself a point  laugh

Melody  Dec 19, 2021