15 laborers dig 40 acres for 40 days how much days wants 20 laborers for 60 acres?

Guest Oct 26, 2014

Best Answer 

 #1
avatar+92382 
+5

If it takes 15 laborers 40 days to dig 40 acres...then they are digging 1 acre per day. And each laborer must dig 1/15 of an acre per day.

So 20 laborers would dig 20(1/15) acres = (4/3) acres per day. So 60/(4/3) = 45 days to dig 60 acres.

 

CPhill  Oct 26, 2014
 #1
avatar+92382 
+5
Best Answer

If it takes 15 laborers 40 days to dig 40 acres...then they are digging 1 acre per day. And each laborer must dig 1/15 of an acre per day.

So 20 laborers would dig 20(1/15) acres = (4/3) acres per day. So 60/(4/3) = 45 days to dig 60 acres.

 

CPhill  Oct 26, 2014

33 Online Users

avatar
avatar

New Privacy Policy

We use cookies to personalise content and advertisements and to analyse access to our website. Furthermore, our partners for online advertising receive information about your use of our website.
For more information: our cookie policy and privacy policy.