+0  
 
0
345
1
avatar

It will take 48 hours of work to complete the garden.The garden must be finished in 3 days.
Each gardener works for 6 hours per day.
How many gardeners are needed?

 Aug 5, 2021
 #1
avatar+37159 
+1

In 3 days each grdener will put in 18 hours

    2 gardeners will work 36 hours

       3 gardeners will manage 54 hours...... so I suggest 3 gardeners to make the 3 day deadline

 Aug 5, 2021

3 Online Users

avatar