+0  
 
0
472
1
avatar

It took $4$ days for $75$ workers, all working together at the same rate, to build an embankment. If only $50$ workers had been available, how many total days would it have taken to build the embankment?

 Aug 26, 2021
 #1
avatar+191 
+4

75workers*4days = 300

50workers*Xdays = 300

 

that X is the answer

 Aug 26, 2021

1 Online Users

avatar