If there are 800,000 documents to be processed in 1 year, how many people it will take to complete the task with a goal of 40 documents an hour per month ( regular 8 hour working day)

 Nov 28, 2016
 #1
avatar+37084 
0

I'll have to make some assumptions ot get an answer

1   4 weeks in a month  (4 weeks vacation per year)

2   40 documents per peson per hour

3   Finsih job in 12 months

 

800000 documents /  40 doc/hr-person x 40 hr/wk x 4 wk/mo x  12 mo   =   10.416     (or 11)  people