To complete a task in 16 days a company needs 5 people each working in 6 hours per day The company decides to have 8 people each working in 4 hours per day Assuming that each person works at the same rate,how many days will the task take to complete
To complete a task in 16 days a company needs 5 people each working in 6 hours per day The company decides to have 8 people each working in 4 hours per day Assuming that each person works at the same rate,how many days will the task take to complete
Since there is an increase in manpower/hours of: [8 x 4] / [6 x 5] = 16/15, therefore, there must be decrease in days by the same pecentage. Or 16 / [16 / 15] =16 x 15/16 =15 days