+0  
 
0
399
2
avatar

150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

 Jan 2, 2020
 #2
avatar
0

IMPORTANT NOTE: NOT MY ANSWER BUT A COPIED ANSWER FROM BRAINY WEBSITE.

 

 

let the work be complete in x days
The work should have been complete by x-8 days.
Total man-days= 150(x-8)
As four worker drop on each day
The total work days are 150,150-4, 150-8..... 150-(x-1)4
These are in arithmetic progression where
                           a1=150  d= - 4 and n=x
so total working man-days= x(2a1-4(x-1))/2
                                      = x(300-4x+4)/2
Then we have 150(x-8)=x(304-4x)/2
⇒  300x-2400= 304x-4x²
⇒  75x-600=76x-x²
⇒  x² -x -600=0
⇒ (x-25)(x+24)=0
solving we have x=25
The work was complete in 25 days.

 Jan 4, 2020

3 Online Users

avatar
avatar
avatar