+0  
 
0
353
3
avatar

Contractor Steve agreed to complete a job in 30 days. After 6 days he found that the 8 people assigned to the work had already done 1/3 of the job. If everyone works at the same rate, what is the least number of people he must keep on the job to ensure that the job will be completed on time?

 Dec 31, 2021
 #1
avatar
0

Steve must keep at least 6 workers.

 Dec 31, 2021
 #2
avatar
0

four workers must be kept to complete 2/3 remaining job in remaining 24 days

 Dec 31, 2021
 #3
avatar
0

Thanks for te help! it is correct(6)

Guest Dec 31, 2021

4 Online Users

avatar