A company hires 16 workers to finish a certain job in 18 hours. If the company wants to shorten the time to 8 hours, then how many extra workers are needed? Assume that all of the workers work at the same constant rate.
1 job takes 16x 18= 288 worker - hours
288 w-h / 8 h = 36 workers