Marvin does four equally time consuming tasks in a row without taking breaks. He begins the first task at 12:00 pm and finishes the third task at 2:00 pm. When does he finish the fourth task?
2 hours for 3 tasks 2/3 hour/task
2:00 + 2/3 hr/task * 1 task = 2:40