A school is arranging a musical production commencing on the evening of the 9th October with the final performance on 15th October. Arrange a Activity table and network diagram to determine the Critical Path for these associated events.
A- Select musical (1 day)
B- Audition performers and determine cast (5 days)
C-Rehearse (6 weeks)
D-Obtain permission from copyright holders (6 weeks)
E-Obtain copies of score (10 days)
F-Design souvenir program (3 days)
G-Send program to printers and await proof copy (2 weeks)
H- Proofread and await copies of program (2 weeks)
I- Order and obtain tickets from printer (3 weeks)
J- Sell tickets (4 weeks)
K- Book hall (1 day)
L- Invite special guests and await replies (2 weeks)
M- Dress rehearsals (1 day)
N- Organising/ Hire costumes ( 4 weeks)
O- Performance (1 week)
Q- Return costumes ( 1 day)
Submit a calendar showing on what day you must start and complete each activity for the musical to occur on the given date.
Identify any potential weaknesses or opportunites to include additonal tasks in your plan